Dear all,
I'm working on a construction contract where the client are insisting the contract programme should have one calendar. The clients planner has even suggested that the NEC contract requires it to be this way. Has anyone come across this in the NEC as I can not find anywhere calendars are discussed?
My main problem is that I represent the Civils contractor and during the summer months we would normally work 6 days a week 10-12 hrs a day. The default calendar would be 40hrs 5 days a week. Some of the other contractors / sub-contractors would only ever work 5 days a week. I can see how a single calendar could be used effectively to create an integrated programme for all construction works... As the principal contractor we are responsible for integrating all of the other contractors programmes and issuing to the client.
Has anyone come across this before?
Replies