Hi
I find it very difficult to plan the SIMOPS into the schedule. Say you have a limited work area and you have hi-pressure activities such as leak tests in that area. When you do the leak tests, all other activities must stop.
What I have done is to mark the hi-pressure activities in a special code and try to push away or bring forward the non-hi pressure activities such that they don't coincide with the hi pressure activities.
Doing this by using predecessors is very time-consuming. But more importantly, because of weather dependency the schedule is very dynamic and every week the sequence may change, in which case all the simops will have to be looked at again. It's a nightmare.
I am using P6 and I wish it had an option of something like "SIMOPS Levelling". For example, it could schedule the activities with its current logic, but make sure they don't coincide with some specially marked activities such as leak tests.
Has anyone come across a similar situation? How do you plan your SIMOPS?
Thanks
Ulkutan
Replies