Can we show this table in MS Project or P6?

7 replies [Last post]
Kashif Khan
User offline. Last seen 10 years 35 weeks ago. Offline
Joined: 17 Nov 2011
Posts: 46
Groups: None
Baseline Vs Actual
Activity I.dAcvtivity NameDurationMonthBaseline % completion (or planned)Actual % completion
1.1Initiation2Jan25%25%
1.2Planning3Feb25%20%
1.3Execution10Mar25%10%
1.4Closing5Apr25%0%

 

 

 

 

 

Hi All,

It is just an image of what is in my mind, i have full programs in p6 as well in ms project but i don't know how to bring the columns like this. it will make my life easier in generating s-curves. can anyone help me?

regards,

KK

Replies

Rafael Davila
User offline. Last seen 3 days 41 min ago. Offline
Joined: 1 Mar 2004
Posts: 5233

Procedure should be similar within your software. If you want detailed % comparison on activity basis you shall create a comparison baseline updated with progress as if planned to the same DD.

Just remember to compare same % types.

Photobucket

Raymund de Laza
User offline. Last seen 9 weeks 3 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hi,

The Schedule % Complete will not roll over to summary unless you will load any resource to an activity. Try adding material type resource even with zero value then you will get the summary value.

Rafael Davila
User offline. Last seen 3 days 41 min ago. Offline
Joined: 1 Mar 2004
Posts: 5233

Create a baseline updated to same DD using progress as planned and then you shall be able to display both columns.

Kashif Khan
User offline. Last seen 10 years 35 weeks ago. Offline
Joined: 17 Nov 2011
Posts: 46
Groups: None

Thanks for this tip, but this schedule% complete does not give overall project summary... it gives updates for the individual activites but does not give overall %age. can we show it from any means?

regards,

Raymund de Laza
User offline. Last seen 9 weeks 3 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Schedule % Complete = Planned % Complete or Baseline % complete

Kashif Khan
User offline. Last seen 10 years 35 weeks ago. Offline
Joined: 17 Nov 2011
Posts: 46
Groups: None

ok, fine but what columns to choose in p6? i cannot find baseline or planned %age in p6.

Raymund de Laza
User offline. Last seen 9 weeks 3 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hi,

Al those data are available from P6 but you need to export to excell to arrange according to the table you wish.

 

Regards,