Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Changing the Data Date and its Impression on Project Milestones

1 reply [Last post]
Ed Afkham
User offline. Last seen 12 years 36 weeks ago. Offline
Joined: 15 Aug 2011
Posts: 7
Groups: None

 

Changing the data date shouldn’t practically push back project milestones.

How do you justify that considering the fact that it pushes back not started activities the same period of data date? 

Replies

Forrest Chen
User offline. Last seen 8 years 24 weeks ago. Offline
Joined: 29 Dec 2011
Posts: 10
Groups: None

Hi,

If it is the first activity (normally a start milestone), then you need to give it a contraint as 'start on';

as for other activities, you can either constrain them (not recommended) or logically link them together.

Hope the above helps with you question.