Hi all Planners,
The Focus of discussion shall be on the The Topic
" Always use Fs Relationship and No Lag"
I was a part of this discussion another forum and was getting different responses,some are as under,
1- Always Use Fs Relationship With no Lag.
2-Always use positive lag with forward pas only and try not to use -ve lag.FS relationship is not necessary (majority oppinion)
3-Use any Relationship (+ve or -ve lag),and keep in focus the logic only.
I agreed with the second point.1st point is also practiceable but not on the large projects where there are thousands of activities and if you split them into further smaller steps to use"FS" Relationship,it will make the plan over crowded.
Secondly if We only use FS relationship the it means that all activities will be critical?? Does it represent a True Scenario??
Any Comments on this topic are wellcomed,
Regards.
AB.
Replies