I want to add quantity(area in sqm or no.s)

4 replies [Last post]
vineeth mathew
User offline. Last seen 12 years 41 weeks ago. Offline
Joined: 3 Nov 2011
Posts: 3
Groups: None

hi planners,

how can i assign and define the area of a project..means the schedule for glazing of a building,the wbs prepared is based on floors-

1st floor,2nd floor etc..

i want to add and show the total area of glass using in each floor and no of doors and windows in each floor..

 

1st Floor

Activity description      Percent complete          Original duration         Quantity

   Doors and windows                0                               9                                 -

       Glazing                              0                               14                               -

 

please reply..

vineeth
 

Replies

In Spider Project this field is called Activity Volume. Volume is a standard field and entering activity Volume and assigned resource productivities you don't need to enter activity duration - it is calculated by the software.

You may define material requirements per unit of volume, unit costs, resource assignment costs depending on volumes performed, etc.

In other softwares you shall use UDF as Mike proposed.

Photobucket

Anand Kurmi
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 10 May 2011
Posts: 4
Groups: None

Hi Vineet,

What mike has written above holds true. Further if you can send me snapshot of the schedul of questioned area i shall be able to answer it

vineeth mathew
User offline. Last seen 12 years 41 weeks ago. Offline
Joined: 3 Nov 2011
Posts: 3
Groups: None

hi mike,

 

sorry to ask u again..if u dont mind please explain..

Mike Testro
User offline. Last seen 21 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Vineeth

You can set up user defined columns for this data or place the information on your resource modelling section.

Best  regards

Mike Testro