Hi fellow planners/schedulers,
I came across something new yesterday and I am not sure how to go about it.
The scope of the project I am involved in changed slightly. It is an engineering project. In my baseline I have a few activities that are not part of the scope anymore. How do I go about that change? Do I simply delete the activities? Do I set its original duration to '0' ( the activity has not started) and unlink it from the rest of the project?
What happens to the budget labor units for that activity? do I delete them as well, or could I move them to an overhead activity?
Any help is highly appreciated. I understand that different projects allow different moves here, but I would like to know what a common industry/good practice approach would be? What do I have to consider when something like this happens?
Thank you very much!