On the edit task/resources tab the crew composition is composed by you - so define it with two crews; after the crew is added then change the supplier from the supplier defined on the general tab to the 2nd crews supplier.
No, by this way the program reduces the duration in each locations. I`ve learned another way: Spliting the task so you choice the locations for each "crew".
I have limited knowledge of Vico but I do recall that you can apply any number of crews to any one task line.
As I recall if you have resourced the task correctly then by moving the end of the distance line horizontally across the time line the number of crews adjust automatically.
Member for
14 years 7 monthsConditonal Yes,On the edit
Conditonal Yes,
On the edit task/resources tab the crew composition is composed by you - so define it with two crews; after the crew is added then change the supplier from the supplier defined on the general tab to the 2nd crews supplier.
Member for
14 years 1 monthHi Mike No, by this way the
Hi Mike
No, by this way the program reduces the duration in each locations. I`ve learned another way: Spliting the task so you choice the locations for each "crew".
Best regards.
José Otávio
Member for
19 years 10 monthsHi Jose I have limited
Hi Jose
I have limited knowledge of Vico but I do recall that you can apply any number of crews to any one task line.
As I recall if you have resourced the task correctly then by moving the end of the distance line horizontally across the time line the number of crews adjust automatically.
Best regards
Mike Testro