Several Crews in Vico Control 2009

3 replies [Last post]
José Otávio
User offline. Last seen 7 years 28 weeks ago. Offline
Joined: 2 Oct 2011
Posts: 8
Groups: None

Hi all,

 

I'm using Vico Control 2009 demo mode and I would like to know if it is possible to put multiple crews in a particular activity. 

Grateful.

Replies

Forest Peterson
User offline. Last seen 8 years 49 weeks ago. Offline
Joined: 22 Mar 2011
Posts: 33

Conditonal Yes,

On the edit task/resources tab the crew composition is composed by you - so define it with two crews; after the crew is added then change the supplier from the supplier defined on the general tab to the 2nd crews supplier.

José Otávio
User offline. Last seen 7 years 28 weeks ago. Offline
Joined: 2 Oct 2011
Posts: 8
Groups: None

Hi Mike

 

No, by this way the program reduces the duration in each locations. I`ve learned another way: Spliting the task so you choice the locations for each "crew".

 

Best regards.

 

José Otávio

Mike Testro
User offline. Last seen 36 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Jose

I have limited knowledge of Vico but I do recall that you can apply any number of crews to any one task line.

As I recall if you have resourced the task correctly then by moving the end of the distance line horizontally across the time line the number of crews adjust automatically.

Best regards

Mike Testro