Hi planners, I am not sure about something contractually.
Lets say
Week 1 - Task A- excavation delayed by information required from architect. 3 weeks EOT granted.
Week 2 – Task B – Construct new foundation, ahead 1 week due to faster excavation compare to tender baseline
Week 3 – Task C – construct walls, 2 weeks faster than the tender programme (tender baseline)
If we look at week 1, the client approved the 3 weeks extension of time but week 2 and week 3, we done the work faster than the tender programme. this neutralise the 3 weeks EOT!
Does this mean I need to give back the EOT?
I am afraid, if I show this 3 weeks ahead, then there will be no delay anymore. What happen task D, E, F, G..... slower than the tender duration due to ourself? I don’t want the client to know I am ahead 3 weeks for itask B and C and no delay now. Just in case the future tasks delay because of ourself and i still have 3 weeks to play around.
just a though from a contractor,
Cheers
Mike
Replies