Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Contract versus programme

1 reply [Last post]
Mike planner
User offline. Last seen 2 years 43 weeks ago. Offline
Joined: 3 Feb 2011
Posts: 46
Groups: None

Hi planners, I am not sure about something contractually.

 

Lets say

 

Week 1 - Task A-  excavation delayed by information required from architect. 3 weeks EOT granted.

 

Week 2 – Task B – Construct new foundation, ahead 1 week due to faster excavation compare to tender baseline

 

Week 3 – Task C – construct walls, 2 weeks faster than the tender programme (tender baseline)

 

 

If we look at week 1, the client approved the 3 weeks extension of time but week 2 and week 3, we done the work faster than the tender programme. this neutralise the 3 weeks EOT!

 

Does this mean I need to give back the EOT?

 

I am afraid, if I show this 3 weeks ahead, then there will be no delay anymore. What happen task D, E, F, G..... slower than the tender duration due to ourself? I don’t want the client to know I am ahead 3 weeks for itask B and C and no delay now. Just in case the future tasks delay because of ourself and i still have 3 weeks to play around.

 

just a though from a contractor,

 

Cheers

Mike

Replies

Mike Testro
User offline. Last seen 1 day 1 hour ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Mike

As usual it all depends on your contract but the usual terms are that once an EoT has been properly awarded it cannot be taken back - except for ommission of work in the final award. This is why contract administrators do not like granting an EoT on the basis of an Impacted as Planned analysis because it is entirely theoretical.

Best regards

Mike Testro