Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P3 versus P5

3 replies [Last post]
Peter Bailey
User offline. Last seen 1 year 24 weeks ago. Offline
Joined: 22 Mar 2006
Posts: 11
Has anybody on here any comments or suggestions re moving from P3.1 to the new P5?

What problems or issues are there? My client is considering moving in the direction of P5 and any info would be appreciated.

Replies

Marcio Sampaio
User offline. Last seen 12 years 9 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
No problem .... i recommend.
Hashim Muhammud
User offline. Last seen 12 years 19 weeks ago. Offline
Joined: 7 Mar 2004
Posts: 38
Groups: None
i think you should be carefull in calendar also. after importing just check the calender in P5 to match with the calanders you had in P3.
Kevin Yue
User offline. Last seen 15 years 49 weeks ago. Offline
Joined: 15 Sep 2006
Posts: 3
No problem, just to double check on the

1)review and adjust WBS
2)review and adjust activites
3)assign resource & cost.

Remember to select Global or project resource coding before you import the P3 file.

Hope it helps