Peter Bailey
User offline. Last seen 1 year 27 weeks ago. Offline
Joined: 22 Mar 2006
Posts: 11
Has anybody on here any comments or suggestions re moving from P3.1 to the new P5?

What problems or issues are there? My client is considering moving in the direction of P5 and any info would be appreciated.

Replies

Marcio Sampaio
User offline. Last seen 12 years 13 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
No problem .... i recommend.
Hashim Muhammud
User offline. Last seen 12 years 22 weeks ago. Offline
Joined: 7 Mar 2004
Posts: 38
Groups: None
i think you should be carefull in calendar also. after importing just check the calender in P5 to match with the calanders you had in P3.
Kevin Yue
User offline. Last seen 16 years 4 days ago. Offline
Joined: 15 Sep 2006
Posts: 3
No problem, just to double check on the

1)review and adjust WBS
2)review and adjust activites
3)assign resource & cost.

Remember to select Global or project resource coding before you import the P3 file.