Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Copying WBS / Activities

1 reply [Last post]
Tanveer Ahmad Niazi
User offline. Last seen 6 years 16 weeks ago. Offline
Joined: 15 Dec 2005
Posts: 151
Groups: GPC Qatar

Hi,

My consultant asked me to make a “Time Impact Program” as we have a new MEP sub contractor whose time of completion is seven months and a lot of civil/architectural work is still left from our side. The extension is given to the MEP works and the finishing work that is following MEP only.  What I did to save time, I created a new program “Clause 14 TIP” and copied the WBS with activities of my existing (that I have already exported/saved on the other drive before maintaining the baseline) into “Clause 14.029” program. I got everything copied into my new program but the “Schedule % Complete” is showing 100% while it is 0% in the original program. I am using P6-V7.0 (stand alone). My questions are;

  • Why is it so?
  • How can I turn that percentage to “0”?
  • Is there any way to copy all resources, units and activities to my time?

Thanx - Cheers

Replies

Dave Ellis
User offline. Last seen 13 years 18 weeks ago. Offline
Joined: 8 Dec 2010
Posts: 7
Groups: None

Hi

Have you somehow managed to bring in the baseline to these activities as well?