Schedule Calculations

1 reply [Last post]
Patrick Weaver
User offline. Last seen 6 days 15 hours ago. Offline
Joined: 18 Jan 2001
Posts: 384
Groups: None

There are a range of options for the calculation of dates and float in a CPM network.

I’ve just finished a draft White Paper focusing on the basic calculations and would appreciate comments on the correctness of the calculations and the methodology adopted.  The aim is to produce a definitive document that is generally agreed. 

You can download the paper from http://www.mosaicprojects.com.au/PDF/Schedule_Calculations.pdf  All comments gratefully appreciated.

Replies

Puneet Gupta
User offline. Last seen 11 years 8 weeks ago. Offline
Joined: 26 Apr 2005
Posts: 92

Patrick:

Your approach for calculation is not correct, You are missing the basic fundamentals.

Also, your Formula "EST = Preceding EFT + [Lag + 1]" is very general. What if I finished Activity A at 18:00 hrs of Day 2 and I am in a position to start Activity B on same day at 18:30 hrs?

On Page 7 of 17 (BackwardPass Calculation) , I could not understand how did you get the LFT for Activity B as 14 and not 11?

In general,

ForwardPass Calculation:

EFT = EST + DUR - 1

BackwardPass Calculation:

LST = LFT - DUR + 1

Regards,

Puneet Gupta

Bau Management + Consulting GmbH