Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

calculate project weight by cost

4 replies [Last post]
Kamyar Sanandaji
User offline. Last seen 13 years 41 weeks ago. Offline
Joined: 16 Oct 2004
Posts: 6
as a factor for weight value of an EPC project In GAS PIPELINE field i want to distribute the weight to my main WBS items in this case i saw lots of discussions that happend in the forum, but nobody didnt mentioned about any refrence that can show how to calculate it for such EPC project, is there any standard or refrence that can modified for these type of projects?

Replies

Kamyar Sanandaji
User offline. Last seen 13 years 41 weeks ago. Offline
Joined: 16 Oct 2004
Posts: 6
No i dont use duration for weight % because it will cause some problem,example: in some activity such as maintenance activities that they have long duration & low weight value Vs. construction works.
Dylan Wan, PMP EVP
User offline. Last seen 9 years 48 weeks ago. Offline
Joined: 9 Mar 2005
Posts: 13
Groups: None
Do you weight your WBS items by their duration? Can you share when you will use "duration" as the weight basis?
Randa Shammas
User offline. Last seen 15 years 45 weeks ago. Offline
Joined: 16 Sep 2004
Posts: 6
Kamyar,

I work for an EPC company as well and this is how weight is usually distributed on the three phases (Engineering, Procurement, and Construction).

For Engineering, % wtg is distributed according to the ENGINEERING MANHOURS needed to produce different engineering documents. This is usually given to you by the different engineering disciplines, and it is your job as a planner to allocate these manhours and distribute them along the engineering phase of your schedule.

For Procurement , weightage is relatively easier to calcuate here since it is based on COST. Basically the more expensive materials / equipment will have a greater % wtg then the less expensive ones.

For construction, weightage is based on QUANTITIES.
Mechanical equipments will be in Tons
Structural Steel will be in Tons of Steel
Concrete pouring will be in m3 concrete.
Electrical and instrument cables will be in Lm
Excavation will be in m3
etc....

there are many many quantities. These quantities should than be transformed into CONSTRUCTION MANHOURS which is done by multiplying by production rates. example: hrs/m3, hrs/ton of steel, etc... These production rate are available here on the plannig planet site. just go to the Prod-rates section. After you’ve got your construction mnhrs ready you have to convert that to % wtg. Roughly the activities with the larger construction mnhrs (aka larger quantities) will have the larger weight factors.

Commissioning I believe is done like construction, but you should check on that cause i’m not sure.

I hope this helped.

Good luck,

Randa
Luca Basile
User offline. Last seen 9 years 41 weeks ago. Offline
Joined: 10 Jul 2003
Posts: 288
Groups: TILOS
Kamyar,
it is a lot in function of the company for which you are working.
I saw different company allocating the weight different.
It depennd in which area the fell stronger.