Dont look jump in. Ask him not to show you how to do thing but rather do them yourself. Example do a progress update. Find out which is the best local pub
Member for
17 years 2 months
Member for17 years3 months
Submitted by Samer Zawaydeh on Thu, 2010-01-14 16:45
In addition to the good information that you got alerady, try to understand the team Dynamics from his perspective. Let him/her take you on a project meeting for each project. You need to get to know the people.
Things change everyday. You might be lucky on the new projects because they do not have a lot of activities. But the running projects are a different thing. You need to be at the location of the project to understand what is going on. This is your next step.
-Current Updated Programme (and any historical / archived progressed programmes)
-Resource Profile
-Cashflow Forecasts
-Project Implementation Plan
-Organogram
-Standard suite of planning reports
Company-specific documents:
-Planning procedures / guidelines, etc
Questions to ask
-What is the standard reporting cycle (weekly, monthly, etc?)
-Map out sequence of activities for planner during standard reporting cycle (are you entering timesheet data? Are you visiting site to update construction progress? Are you getting eng & proc progress from team members, team leaders, progress meetings, etc? Are you tracking plant & material utilisation? Ad nauseum)
-How much attention is paid internally to the schedules you will be producing? (Particularly relevant during the engineering phase. –Design engineers often see forecasting & progress reporting as nothing more than red tape which gets in the way of doing their real jobs)
-What current (planning) issues are there on the current jobs –any outstanding or pending claims / LD issues?
-Can I contact you for support in the future? (since the guy you’re replacing is staying within the same firm)
-What involvement can I expect to have on future bids / projects (tendering phase, contract negotiations, etc)
-Whats the relationship like with our clients?
That’s probably about as much as you could reasonably cover in 2 days
Member for
17 years 4 monthsRE: No Subject Specified
Dont look jump in. Ask him not to show you how to do thing but rather do them yourself. Example do a progress update. Find out which is the best local pub
Member for
17 years 2 monthsRE: No Subject Specified
Dear Raul,
In addition to the good information that you got alerady, try to understand the team Dynamics from his perspective. Let him/her take you on a project meeting for each project. You need to get to know the people.
Things change everyday. You might be lucky on the new projects because they do not have a lot of activities. But the running projects are a different thing. You need to be at the location of the project to understand what is going on. This is your next step.
With kind regards,
Samer
Member for
19 years 10 monthsRE: No Subject Specified
Hi Raul
The two most important questions to ask when starting a new job:
Where is the tea room.
Where is the gents.
All else is secondary.
Best regards
Mike Testro
Member for
16 years 7 monthsRE: No Subject Specified
Of the top of my head:
Project-specific documents:
-The Contract
-Tender Package
-Baseline Programme
-Current Updated Programme (and any historical / archived progressed programmes)
-Resource Profile
-Cashflow Forecasts
-Project Implementation Plan
-Organogram
-Standard suite of planning reports
Company-specific documents:
-Planning procedures / guidelines, etc
Questions to ask
-What is the standard reporting cycle (weekly, monthly, etc?)
-Map out sequence of activities for planner during standard reporting cycle (are you entering timesheet data? Are you visiting site to update construction progress? Are you getting eng & proc progress from team members, team leaders, progress meetings, etc? Are you tracking plant & material utilisation? Ad nauseum)
-How much attention is paid internally to the schedules you will be producing? (Particularly relevant during the engineering phase. –Design engineers often see forecasting & progress reporting as nothing more than red tape which gets in the way of doing their real jobs)
-What current (planning) issues are there on the current jobs –any outstanding or pending claims / LD issues?
-Can I contact you for support in the future? (since the guy you’re replacing is staying within the same firm)
-What involvement can I expect to have on future bids / projects (tendering phase, contract negotiations, etc)
-Whats the relationship like with our clients?
That’s probably about as much as you could reasonably cover in 2 days