Hello Everybody,
Can you please advise me how to trace and show Critical Activities?
Here are the scenarios:
We have about 2000 activities in our programme. However, we are already behind by 4 months (112 days) based on current schedule against baseline.
The Client asking me to submit weekly the critical activities based on current updated programme. What I did, in order to trace my critical activities I applied the constraint to all my milestone finish date (Finish on or before Constraint). Because what I know, this is the only way how to trace critical activities. Since our Client, does not allow us to put the "Project Must Finish By" date.
My main problem is, the Client again does not allowed us to apply the constraint in the milestone as well as in the activities.
My question is, is there any way, how to show the critical activities in the current schedule? I tried to remove the constraint; however the current schedule gives me only 5 numbers of critical activities which is not correct.
All suggestions are welcome especially to the experts.
Thank you and best regards,
Aryan
Replies