Fully agree with you regarding the link to how good the systems in house are for timesheet, financial and archiving.
You have added the function of Doc. Controller which I would replace with change management.
The new systems for document control become so sophisticated and time consuming.
I would say: for a FEED with man-hours less the 100 K, one person is enough to manage the following: schedule, progress measure, cost control and change management.
regards,
Member for
16 years 7 months
Member for16 years7 months
Submitted by Gary Whitehead on Tue, 2009-06-16 06:30
When Ive worked on FEED or other home-office projects, the PC team tends to be 1 scheduler / progress measurer (me), 1 cost control/accountant and 1 Doc controller.
This team then runs all PC for all projects in the office.
Id estimate total of, say, 100,000 man-hours of projects could be handled in this way. So maybe 1/3 of that for a single person to handle all 3 roles.
Obviously it very much depends on how good/automated your systems are for timesheets, financial reporting, archiving, etc
Member for
21 years 4 monthsRE: Project control - one person only
Hi Mike,
FEED = Front end engineering design
OR Basic Engineering.
It is not exactly the same in terms of the deliverables to be issued as part of the FEED or basic engineering.
regards,
Member for
19 years 10 monthsRE: Project control - one person only
Hi Gary Hi Carmen
What is a FEED project?
Best regards
Mike Testro
Member for
21 years 4 monthsRE: Project control - one person only
Gary ,
Fully agree with you regarding the link to how good the systems in house are for timesheet, financial and archiving.
You have added the function of Doc. Controller which I would replace with change management.
The new systems for document control become so sophisticated and time consuming.
I would say: for a FEED with man-hours less the 100 K, one person is enough to manage the following: schedule, progress measure, cost control and change management.
regards,
Member for
16 years 7 monthsRE: Project control - one person only
Hi Carmen,
When Ive worked on FEED or other home-office projects, the PC team tends to be 1 scheduler / progress measurer (me), 1 cost control/accountant and 1 Doc controller.
This team then runs all PC for all projects in the office.
Id estimate total of, say, 100,000 man-hours of projects could be handled in this way. So maybe 1/3 of that for a single person to handle all 3 roles.
Obviously it very much depends on how good/automated your systems are for timesheets, financial reporting, archiving, etc
Regards,
Gary