UPDATED FINISH MILESTONE?

Member for

17 years 5 months

Arnold, that is a great comment! I needed that... "Finish Milestone should not have a time-based cost/expense."



Cheers!

Member for

18 years 6 months



Finish Milestone may have a primary resource and expenses associated with it, but cannot have a resource assignments, role assignments, or time-based costs such as labor.

Member for

17 years 5 months

I respect ur views Arnold. Maybe we have to wait for other’s comments.

Member for

17 years 5 months

Finish Milestone can be loaded, specifically with cost, which is acceptable for me or by others. The inappropriate thing that the contractor did is updating in less than 100% or updating it at certain percentages only. That is why I see that wrong.

Member for

18 years 6 months

Hi Marwan,



If I understood you, a Finish Milestone cannot be loaded with resources because, it is zero duration.



Regards,



Arnold