Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

UPDATED FINISH MILESTONE?

6 replies [Last post]
marwan ibrahim
User offline. Last seen 15 years 27 weeks ago. Offline
Joined: 28 May 2008
Posts: 31
Our contractor updated a finish milestone, cost loaded, to reflect a certain percentage of accomplishment. I see this wrong. Comments please.

Replies

marwan ibrahim
User offline. Last seen 15 years 27 weeks ago. Offline
Joined: 28 May 2008
Posts: 31
Arnold, that is a great comment! I needed that... "Finish Milestone should not have a time-based cost/expense."

Cheers!
Arnold Puy
User offline. Last seen 9 years 39 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

Finish Milestone may have a primary resource and expenses associated with it, but cannot have a resource assignments, role assignments, or time-based costs such as labor.
marwan ibrahim
User offline. Last seen 15 years 27 weeks ago. Offline
Joined: 28 May 2008
Posts: 31
I respect ur views Arnold. Maybe we have to wait for other’s comments.
Arnold Puy
User offline. Last seen 9 years 39 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

I don’t think so.

Arnold Puy
User offline. Last seen 9 years 39 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Marwan,

If I understood you, a Finish Milestone cannot be loaded with resources because, it is zero duration.

Regards,

Arnold

marwan ibrahim
User offline. Last seen 15 years 27 weeks ago. Offline
Joined: 28 May 2008
Posts: 31
Finish Milestone can be loaded, specifically with cost, which is acceptable for me or by others. The inappropriate thing that the contractor did is updating in less than 100% or updating it at certain percentages only. That is why I see that wrong.