Finish Milestone may have a primary resource and expenses associated with it, but cannot have a resource assignments, role assignments, or time-based costs such as labor.
Member for
17 years 5 months
Member for17 years5 months
Submitted by marwan ibrahim on Wed, 2009-04-01 04:00
Finish Milestone can be loaded, specifically with cost, which is acceptable for me or by others. The inappropriate thing that the contractor did is updating in less than 100% or updating it at certain percentages only. That is why I see that wrong.
Member for
17 years 5 monthsRE: UPDATED FINISH MILESTONE?
Arnold, that is a great comment! I needed that... "Finish Milestone should not have a time-based cost/expense."
Cheers!
Member for
18 years 6 monthsRE: UPDATED FINISH MILESTONE?
Finish Milestone may have a primary resource and expenses associated with it, but cannot have a resource assignments, role assignments, or time-based costs such as labor.
Member for
17 years 5 monthsRE: UPDATED FINISH MILESTONE?
I respect ur views Arnold. Maybe we have to wait for others comments.
Member for
18 years 6 monthsRE: UPDATED FINISH MILESTONE?
I dont think so.
Member for
17 years 5 monthsRE: UPDATED FINISH MILESTONE?
Finish Milestone can be loaded, specifically with cost, which is acceptable for me or by others. The inappropriate thing that the contractor did is updating in less than 100% or updating it at certain percentages only. That is why I see that wrong.
Member for
18 years 6 monthsRE: UPDATED FINISH MILESTONE?
Hi Marwan,
If I understood you, a Finish Milestone cannot be loaded with resources because, it is zero duration.
Regards,
Arnold