I saw the reason why your Performance % & Schedule % complete does not roll-up in your summary is because, when the time you assigned your resources to your activities, you did not mark the checkbox next to "Auto Compute Actuals" & "Calculate cost from units" from Resources workspace --> Details Tab.
Before you will assign all resources to your activities you must mark the checkbox in order to calculate automatically the budgeted & actual cost during updating.
Try to notice your current updated activities that some of them is zero for budgeted & actual cost even your price/unit is not equal to zero.
I tried and check your suggestion but unfortunately none of it have worked out. I also tried to redo the same program, but the result is still the same.
If activities have been added that arent included in the baseline this can happen. If this is the case update the baseline with a filter to include the new activties.
RE: WBS Sched% compl & Perf % compl inquiry
You are welcome George.
RE: WBS Sched% compl & Perf % compl inquiry
Hi Arnold & Mark,
Thanks for your help.
I really appreciate your kindness. Keep up the good work and please dont be tired helping others.
Problem solved.
Regards,
George
RE: WBS Sched% compl & Perf % compl inquiry
Hi George,
I saw the reason why your Performance % & Schedule % complete does not roll-up in your summary is because, when the time you assigned your resources to your activities, you did not mark the checkbox next to "Auto Compute Actuals" & "Calculate cost from units" from Resources workspace --> Details Tab.
Before you will assign all resources to your activities you must mark the checkbox in order to calculate automatically the budgeted & actual cost during updating.
Try to notice your current updated activities that some of them is zero for budgeted & actual cost even your price/unit is not equal to zero.
Try to check and let us know.
HTH.
Regards,
Arnold
RE: WBS Sched% compl & Perf % compl inquiry
You are welcome.
My e-mail address is primavera6@live.com
You can it now since I am still free.. I will just try..
Thanks.
RE: WBS Sched% compl & Perf % compl inquiry
Hi arnold,
thanks for your kindness. can i have your email add. i cant send in your pm ( i think its under mtce now)
thanks again.
RE: WBS Sched% compl & Perf % compl inquiry
Hi George,
Sorry... If you dont mind, send me your .xer file and I will try to fix for you.
Regards.
Arnold
RE: WBS Sched% compl & Perf % compl inquiry
Hi George,
If you mind, send me your .xer file and I will try to fix for you.
Regards.
Arnold
RE: WBS Sched% compl & Perf % compl inquiry
Hi Arnold,
thanks for your help. i tried your suggestion and tried to redo the program several times, but stilll getting the same result.
I think my primavera is corrupted.
Thanks & regards,
George
RE: WBS Sched% compl & Perf % compl inquiry
Hi George,
Do you have a baseline in your programme? If yes, then you need to update your Baseline the same with your current. Otherwise, it doesnt not works.
Try to check and let us know. As far as I know, this is the reason why it does not show. Performance % complete is related to money.
HTH.
Regards.
RE: WBS Sched% compl & Perf % compl inquiry
Hi George,
Do you have a baseline in your programme? If yes, then you need to update your Baseline the same with your current. Otherwise, it doesnt not works.
Try to check and let us know. As far as I know, this is the reason why it does not show. Performance % complete is related to money.
HTH.
Regards.
RE: WBS Sched% compl & Perf % compl inquiry
Thanks guys for your prompt reply.
I tried and check your suggestion but unfortunately none of it have worked out. I also tried to redo the same program, but the result is still the same.
am I missing out something here....
thanks...
RE: WBS Sched% compl & Perf % compl inquiry
Hi George,
In addition to what Marks info. Try to check also your Price/unit for Resources should not be equal to zero.
Regards.
RE: WBS Sched% compl & Perf % compl inquiry
Hi George
If activities have been added that arent included in the baseline this can happen. If this is the case update the baseline with a filter to include the new activties.
Hope that helps.
Regards
Mark