Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Thumb rules to assing the resources

18 replies [Last post]
Ahmed Khan
User offline. Last seen 15 years 22 weeks ago. Offline
Joined: 3 Dec 2008
Posts: 29
Do any one knows about the thumb rules to assing the resources to a P3 programme...?

The normal activities are
Excavation
Blinding
Consolidation
Water proofing
Construction of wall ( 20M ht)
Back filling... etc....

Replies

Se de Leon
User offline. Last seen 2 years 49 weeks ago. Offline
Joined: 15 May 2001
Posts: 321
Groups: None
Hi Maask,

Are you looking for rule of thumb productivity rates? If you’re looking for a standard rates then, you could check the productivity rates in PP, or you can check R.S. Means. There are more but the above are some of the references I’m using plus more importantly, based on experience rates.

Don’t rely solely on these references because these could only become a close approximation of your assigned resources depending on many factors like weather, available crew, available materials, how experienced are your crew how tight is your working area and many more. In other words, actual experience and common sense will play the bigger part.

I hope this helps.
R. Catalan
User offline. Last seen 12 years 20 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 314
Groups: None
Maask,

One is, if you assign more than one driving
resource to an activity, the longest calculated resource duration determines the activity’s remaining duration.





Mike Testro
User offline. Last seen 17 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Alex

BOQ - Cost Plan - same thing.

Best regards

Mike Testro
Alex Wong
User offline. Last seen 11 years 16 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
How about your BOQ??

Anoon Iimos
User offline. Last seen 2 years 26 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Maask,

The basis would be:

1. Quantity of Work(s)
2. Productivity Rates
3. From the above two items, you can assign your intended units per day (or units per planning unit). For me, that is straightforward.
Mike Testro
User offline. Last seen 17 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Maask

We are getting into resource modelling now - what software are you using?

Generally the resource modelling aspect of planning software works the same.

Hours = the work to be done for each section extracted from the cost plan.
Allocation = the gang to be set on each work section.

You do not need production rates because you have bypassed that requirement.

For instance in the cost plan there is a total sum of £15,000 for brickwork - this is how I extract the hours:
Brickwork

Cost Plan £15,000.00
Profit & O/Head 10.00%
Net Value £13,636.36
Labour % 35.00%
Labour Value £4,772.73
Labour rate £18.00
Labour Hours 265.15

The hours are then distributed pro rata to where bickwork tasks are on the programme.

The gang sizes are set as appropriate.

The resource modelling is set to show "duration" based on "Hours" balanced by "Gang".

In PowerProject all this data can be copy / paste from the spreadsheet so it only amatter of minutes to set up.

In P3 you have to enter every bit by hand - maybe a day or two.

Best regards

Mike Testro
Ahmed Khan
User offline. Last seen 15 years 22 weeks ago. Offline
Joined: 3 Dec 2008
Posts: 29
Dear all,

Hope U all understands my problem, Still I want to simplify, I want to assign the Budgeted Quantities for the below mentioned ( Like that) activities in HOURS.
Do we have any thumb rules..? If not can we create it..?

Can any one give me the solution of problem.

Thanks & Regards,
Maask
Ahmed Khan
User offline. Last seen 15 years 22 weeks ago. Offline
Joined: 3 Dec 2008
Posts: 29
Mike Testro,

Thanks for the mail,

The same thing I am also considering the resource called “Hours”
But to assign them to the activities which I mentioned below, Is there any specific thumb rules..?

Thanks & Regards,

Maask
Ahmed Khan
User offline. Last seen 15 years 22 weeks ago. Offline
Joined: 3 Dec 2008
Posts: 29
Samer,

Thanks for the mail,

The production rates is totally dependent upon our actual resources. It is not accrding to the planned.

But I want to assign the resources according to quantity calculated.


So is there any thumb rules to assign the resources…?

Thanks & Regards

Maask
Ahmed Khan
User offline. Last seen 15 years 22 weeks ago. Offline
Joined: 3 Dec 2008
Posts: 29
Arman

Thanks for the reply.

I am looking for quit same thing but still it doesn’t meets my requirements. The quantities for instance:

Excavation (120 Cu M)
Consolidation (30 Cu M)
Concreting (250 CuM)
Shuttering (1000 Sq M)
Scaffolding (500 Sq M)
Back filling (400 Cu M)… etc… are the quantities which I’ve calculated, and according to the quantities I want to assign the resources.
Instance, For excavation I need the Labour General, Labour Operatives etc… So how do I assign these resources to the activity.
So my final question is “ Is there any thumb rules to assign the resources to such an activity..?

Thanks & Regards
Maask
armando moriles
User offline. Last seen 13 years 19 weeks ago. Offline
Joined: 2 Feb 2003
Posts: 66
Groups: None
Maask,

I forgot the proposed resource crewing system...

4man scaffolding team
8man forms team
10man rebar fixing team (excluding cut and bend team)
8man concrete pouring team (if pouring extends more than 8 hours, forms and rebar team may assist)
1 rigging team
1 survey team (part time0
1 welder (if required)


regards,
Arman
Arman
armando moriles
User offline. Last seen 13 years 19 weeks ago. Offline
Joined: 2 Feb 2003
Posts: 66
Groups: None
Maask,

Suggetion for your reference for the construction of your 20M high wall:

@ 3M lift, you have 7 lifts total;
@ 3 uses refurbishment cycle for 3/4" thick ordinay plywood;

reference 120m2 forms concrete contact area/lift
total forms concrete contact area = 120m2 x 7 = 840 m2
Using 3/4" ordinay plywood as forms @ 3 Plywoods/set
no. of sets = 14 (7 each face)

scaffolding 1 day
Fix rebar 4 days (highly variable depending upon no. of resources)
Fix forms 1 day plus 1 day if there are cast-in plates
QA & survey check, final adjustments, sign off for pouring 1 day
Pouring 1 day
Strip/clean Form 1 day
cycle total 9 days/lift + 1 day for CIP(if any)

total duration = 9 days/lift x 7 lifts = 63 days
plus:
10 days allowances for forms refurbishments and other delay allowances = 73 days

equipment : 1 mobile crane
rebars : within 5-10m from structure

Backfilling works after structure is completed, cured and vibration secured.

If you intend to backfill after each lift to get rid of high scaffolding system, the cycle time is different and long.


Regards and hope it helps...

Arman








Samer Zawaydeh
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear friend,

The production rates for the following activities depends on the number of machines and manpower you have on site to complete the job. For a small/medium size job, you can consider the following production rates

Excavation: 1000m3/ days for soil strength around 2
Blinding: 1000m2/ day depending on the number of pumps.
Consolidation: If you mean Fill, you can go up to 1500m2/day per 20cm layer
Water proofing: 100m2/day / 2 manpower (vertical walls)
Construction of wall ( 20M ht): too general.
Back filling... etc....: depends on location, between footings or open areas (100-500m2) compacted with testing.

The above figures are too general. The best source for information would be your site engineers and supervisors doing the job.

Best,

Samer
Mike Testro
User offline. Last seen 17 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Maask

There are three factors to take into account.

1. Volume of work
2. Appropriate production rate
3. Gang size

The work volume is taken from the cost plan.

An experience planner will have access to a number of production rates - the skill is in determining which one is appropriate ie hand fixed rebar or prefabbed rebar.

The gang size relates to how many people are available plus how many can be put in one location.

For simplicity I only use one resource called "hours".

The resource hours can be extracted from the cost plan by use of labour content % / local labour rate.

The resource hours are then allocated to the relevant activities and a suitable gang size selected.

The durations are then modelled by the software.

Best regards

Mike Testro
Ahmed Khan
User offline. Last seen 15 years 22 weeks ago. Offline
Joined: 3 Dec 2008
Posts: 29
Arlene Cananan,
I dont get it. Could U plz give me the classifications where exaclty it is,,?
Thanks & Regards
Azeem
Rlin C.
User offline. Last seen 3 years 44 weeks ago. Offline
Joined: 8 Feb 2008
Posts: 11
Dear Maask,

If you meant computation of manpower resource, refer to Prod-Rates in this website. There are rule of thumb rates listing.

Regards,
Arlene
Ahmed Khan
User offline. Last seen 15 years 22 weeks ago. Offline
Joined: 3 Dec 2008
Posts: 29
Dear Samer,
Thanks
But i want to know the thumb rules. I meant the distribution of labour resources to the below mentioned activities.

Regards
Azeem
Samer Zawaydeh
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Maask,

To assign the resources in P3 you will need to go to the Resource Dictionary.

Press "Data" then "Resouces", then you will get the "Resource Dictionary". You can add the manpower, machines as you like.

Best Regards,

Samer