Showing "Non Working days" on Gantt chart
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Probably your client needs a basic explanation on why necking is used.
Is there any way of blanking out the non work time so it only shows when work is being done? I've a client who can't get their head around the idea of the necked bars.
thanks
Is there any way of blanking out the non work time so it only shows when work is being done? I've a client who can't get their head around the idea of the necked bars.
thanks
Is it possible to have multiple curtains over a period of time?
Ans: Yes! Just re-do the curtain days and you will have multiple curtains.
Mark,
That is exactly what I was after, a curtain!!
That you very much - I was proven wrong as I insisted this was not possible in P 5.0!
Thanks again!
Regards
Ben Hall
Mark,
That is exactly what I was after, a curtain!!
That you very much - I was proven wrong as I insisted this was not possible in P 5.0!
Thanks again!
Regards
Ben Hall
Hi Ben,
You can show the Gray Color in Column in the Gantt Chart Area representing the Non Working Days. To do this, you need to assign the calendar as your default calendar by marking the checkbox in calendar box.
Then try to adjust your Timescale to Month/week so that you can see the gray color.
HTH.
Arnold
Hi Ben
I think what you a referring to is a curtain. If you right click in the Gantt chart window and select "attachments", "curtain", "Add curtain". You can then detail which dates you want the curtain to show, this can be repeated if required.
Hope that helps.
Cheers
Mark
Hey Arnold,
I have done that thanks, and yes it does show the breaks in the activities.
Though i have been told that Primavera can show a darkened column over the week which is Non-Workings..say this week - wk 43..if this was a holiday week i want to show the wk 43 column on the gannt chart "darkened out or blacked ou" so you can straight away know its a Non-Working week.
Does this make sense?
Is it possible?
Your prompt reply is greatly appreciated!
Thanks & Regards
Ben Hall
Hi Ben,
Go to View --> Bars --> Early & Critical Bar, in Bar Setting under Bar Necking Settings mark the box next to "Calendar nonwork time" when done select OK.
HTH.
Arnold