I just started a thread in the P3 forum to check if its CPM algortithm does the same as MS Projects (and every other Ive ever seen).
Try the following project:
A 10d No preds
B 10d Pred: A/FS0
C 10d Pred: B/FS0
D 5d Preds: A/FS0, B/FF5
E 10d Pred: D/SS5
F 10d Preds: D/FS, E/FS
All the software packages Ive ever seen will:
1. Give a project duration of 45 days, when, if there are no other constraints, it can be completed in 40.
2. If you want to shorten the project duration below 45, just ADD time to Activity D -- make it 8d and watch what happens to the project finish date.
3. If you shorten Activity D (which the s/w will say is on the CP), the project will actually become longer!
4. The s/w will say that Activity D and E are on the CP, and Activity C is not. The opposite is actually true.
I wonder how many dollars (and lives!) are lost because of this computation issue?
Replies