Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Procedure Of Re-bar fixing

6 replies [Last post]
Jim Tse
User offline. Last seen 17 years 5 weeks ago. Offline
Joined: 13 Jun 2007
Posts: 6
Groups: None
Dear all,

I am carrying out a study on "Productivity Rate of Rebar fixing". Since I have little site experience and this prevents me from carrying out the study.

May I ask you all ,experienced professionals, the comprehensive procedure of re-bar fixing on site? Thus, I can better prepare myself for the measurement.

THX alot!

Replies

ashraf alawady
User offline. Last seen 10 years 5 weeks ago. Offline
Joined: 26 Aug 2006
Posts: 320
Groups: None

Hi,

 

some facors which are affecting the productivity of rebar fixing :-

condition of the working area

nubmer of available steel fixers

effecitncy of the steel fixers

number of the assistants

number and condition of the requered equepments and tooles for lifing, cuttig , bending.......the rebar

complexity of the reinforcement

the diameter of the steel bar

 

Regards

 

Abhishek Shah
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 28 Aug 2012
Posts: 3
Groups: None

Dear Arman

I am a Quantity Surveyor , in estimation dept and i want to cross check the quantities which i have calculated

Like concrete, Rebar, Formwork based on Builtup area or any thumb rule.

I just want to check that i am not making a major mistake in Calculations...

Thankyou

Abhishek Shah
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 28 Aug 2012
Posts: 3
Groups: None

Dear Arman

Can you share "Productivity Rate" with me also , It will help me too...

My email Add - abhipivot02@gmail.com

regards

Abhishek

Armando Moriles
User offline. Last seen 17 years 2 days ago. Offline
Joined: 9 Dec 2005
Posts: 104
Groups: None
Jim,

What’s your email ad?


Arman
Jim Tse
User offline. Last seen 17 years 5 weeks ago. Offline
Joined: 13 Jun 2007
Posts: 6
Groups: None
Dear Arman,

I am very happy that you can reply me with such a detail explanation! I am sure you must be one of these professionals.

Actually, my study aims at searching for the factors that affecting the re-bar productivity. I hope you can also figure out these factors as soon as possible.

Lastly, thx again for your kindly and promptly help.

Jim
Armando Moriles
User offline. Last seen 17 years 2 days ago. Offline
Joined: 9 Dec 2005
Posts: 104
Groups: None
Hi Jim,

I’m not really one of those experienced professionals that you expected to reply. But like you, I am also interested to improve further my knowledge regarding the world of productivities and the factors affecting those productivities.

I would like to share my experience as follows:

>Foundation Type: Building Mat Foudation
>Slabs/Foundations Steel Fixing Productivity: 20 manhour/ton (High) and 30mh/ton (low)
>Equipment Used: 25t Mobile Crane but only 1/3 of the area is within working radius of the crane (NO TOWER CRANE).
>Tools Used: Chain pullers for alignment of installed rebars and air compressor for cleaning prior to pouring.

Works Inclusive: Unloading of rebars from delivery truck using mobile crane then sorting, installation of spacers & chairs, clean-up prior to conrete pouring using compressed air, alignment of installed rebars.

Works Exclusive: Fabrication, loading of rebar from fabrication to delivery truck.

Working Hours/day: 8 productive hours exclusive of breaktimes.


IMPORTANT NOTES:

1. If you try to look at the productivity of the same activity published here PP Production-Rates,you will notice that it is way very different. It is because I don’t know how it is being derived or where it is coming from.I have no idea why is it so, rather, that is what I wanted to find out actually. The factors that affect that specific productivity;
2. You will also notice that I specified the number of productive hours/day. It is because I have records in one of our previous projects that steel fixing during overtime hours their productivity was faster than the figure I specified above; and
3. Lastly, the fast production rate is what I believe was my perfect and ideal condition rate. The labour effectiveness factors that I gathered for my low rate are still inconclusive being subject to further data gathering, comparissons and evaluations.

PROCEDURE OF REBAR FIXING:

1. Survey set-out (Coordinates and elevation);
2. Set-up temporary scaffolding systems (Beam height above 1m);
3. Fix beam bars;
4. Fix mat bottom bars;
5. Install steel chairs;
6. Fix mat top bars;
7. Fix column rebar stumps;
8. Alignment using chain pullers;
9. Survey final check;
10. Concrete pour bottom slab of mat foundation;
11. Form and pour beams;
12. Water proofing;
13. Backfilling and compaction; and
14. Slab on Grade Works.
10. Quality check and sign off



Regards,


Arman