No manpower in lumpsum cost

1 reply [Last post]
ulysses garcia
User offline. Last seen 13 years 30 weeks ago. Offline
Joined: 22 Aug 2005
Posts: 259
Groups: GPC Qatar
Hi all,

Is it technically correct not to put manpower unit in the schedule in a lump sum cost contract.

Replies

Dieter Wambach
User offline. Last seen 7 years 17 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Ulysses,

In most of the cases: Yes, because you are just interested in the result, not in the manpower the the contractor needs.
But there are exceptions, where you need/want to know labour units, e.g. how many persons will be within the construction area at a time or simply to check if a contractor’s planning is realistic.
Regards
Dieter