Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Benchmarking schedule data

6 replies [Last post]
Carmen Arape
User offline. Last seen 7 years 11 weeks ago. Offline
Joined: 26 Jun 2004
Posts: 292
TO Level 1 Planners,

Does anyone have information about benchmarking schedule data (CHEMICAL field).

CONSTRUCTION : Duration estimate for a polymers plant with following features:
CAP; 150000 ton/yr . Two lines.
Output is: POM (polyoxymethylene flakes).

Thanks,
carmen

Replies

Carmen Arape
User offline. Last seen 7 years 11 weeks ago. Offline
Joined: 26 Jun 2004
Posts: 292
PETER,

Thanks for the reference to IPA. In its website, they state a detailed process plants database for more than 4,200 projects for comparison. May be, the database is ONLY Cost database. I will get in contact with them.

Peter, I got a very standard delivery of 35 months execution, starting with FEED to Mechanical completion (no RFSU).

My need of benchmarking schedule data is due to have more arguments for defending my schedule developed during proposal stage. During this phase, no much information is available.

Cheers,
carmen
Peter Holroyd
User offline. Last seen 6 weeks 6 days ago. Offline
Joined: 6 Jun 2005
Posts: 162
Carmen,
trouble with this thread and its analysis (for most Polymer Plants) is that it doesn’t recognise the total schedule dependence on the Long Lead Equipments Items and whether any pre contract arrangements have been made by the Client.
Typically for Basic to RFSU we will have 28 months for a world class delivery schedule against 36 months for standard delivery.
Bearing in mind that into these schedules typically equipment delivery times can be 24 to 32 months (increasingly heading for 36 months). The only difference is whether the Client (or its PMC)has pre-ordered the key equipment.
If you want to know more about benchmarking see the IPA website - but unfortunately real data means you have to pay to join the club!!
Charleston-Joseph...
User offline. Last seen 3 years 14 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Carmen,

Our understanding is different.

Using your figures, I arrivea at the following:

Design (Detailed Engineering): 8 months = 25%
Procurement (All inclusive ETA at site): 9 months = 28%
Construction: 11 months = 34%
Testing and Commissioning: 4 months = 13%

so it is different, benchmarck is different.

Wait for few days, i may come up with some figures for Polymer Plants that will take 30 months to complete.

Cheers,

Charlie
Carmen Arape
User offline. Last seen 7 years 11 weeks ago. Offline
Joined: 26 Jun 2004
Posts: 292
Hi Charleston,

Thanks, but please give me more clues about your figures:

1.- Shall I use your figures for estimating durations ?? If it is so, I have a EPC Schedule for new Polymer plant which takes 30 months. Using your figures, I should estimate the following:

Detailed Engineering : 8 month
Procurement : 9 month (I assume that procurement means Issue RFQ untill POrder award)
Construction: 11 months
Testing, Commissioning : 4 months.

What I got on my schedule is fully different

Cheers,
Carmen
Charleston-Joseph...
User offline. Last seen 3 years 14 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Hello Carmne,

I hope this will start the ball rolling.

Design (detailed Engineering) = 24 %

Procurement = 28 %

Construction = 36%

Testing and Commissioning = 12 %

Cheers,

Charlie
Carmen Arape
User offline. Last seen 7 years 11 weeks ago. Offline
Joined: 26 Jun 2004
Posts: 292
Dear Level 1 Planners,

To my utter astonishment, 41 planners took a look to my thread BUT no answer. Why ???

I think that the problem is the word benchmarking. Let’s clarify this term which seems to be new in market or it was new to me.

“Benchmarking is the process of determining who is the very best, who sets the standard, and what the standard is”

Based on that, I was developing an EPC schedule at proposal stage of a project. For this reason, I thought BENCHAMARKING is the ideal tool for determining rough duration for level 1 EPC.

I used durations based on historical data of my Company. BUT may be we are not best, for this reason I tried to get benchmarking schedule data. Main purpose was to compare my durations with someone who might be setting the standard of BEST Durations for:
Detailed Engineering
Construction

Welcome any comment
Cheers,
carmen