There are many things that help to track the progress of the project. Materials are one. You must track your shop drawings (being submited by sub-contractors and approved by the architect) to insure that materials are recieved in a timely fashion so as not to delay progress. You should define items with long leed times. One item might delay several sub-contractors or delay the entire project. Even though you show progress as work complete to date compared against a baseline you need to track your materials. This is an important factor in schedualing a project.
well, i think it went back to the same statement (..work execution should be measured in its own appropriate resource...). i think, it represents, a fact, that, every activity has its own way of evaluation and measurement.
my regargs for all,
mohd
I think the best solution to this discussion is EVPM.
Each activity's progress is measured in it's own units, translated to percent complete and used to compute earned value.
In this environment, the A/C unit discussion looses relevance, since all you do is compare a budget against a real progress.
The point is how much does each activity contribute to the whole effort. Well, you can manage that computing earned value in either dollars, man-hours, steel tons, concrete M3, etc.
Progress acomplished, by itself, does not really mean anything useful. What is more important is how much we have acomplished compared to our baseline progress metrics. In other words, have we acomplished as much as we need to, to date? You can measure this in terms of cost, duration or any resource metrics. It does not really matter as long as you are consistent with your measurements. Better yet, you should have two progress baseline curves. One for the earliest baseline schedule and another for the latest baseline schedule. Your actual progress should fall in between these two curves.
One word of caution: progress is only one side of the coin for making sure our project is on track.
I definitely agree, in our practice, we measure progress based on physical accomplishment. It not good to report that a particular equipment is there, of it is not installed it is still not a deliverable. It does not serve its function.
no body can disagree with that statement "work execution should be measured in its own appropriate resource" as progress measurements varies with every recourse involved and its activity. as far as electromechanical contractor, installing A/C chiller, is an important milestone. and for a civil one, block works is a time consuming activity. for a main contractor, who needs to know when will pay that much.
I do not agree with your with regard to cost, take and example of the A/C Chiller it costs a lot compared to 1 m sq of render lets say. When I deliver this chiller to site that does not mean that I have progressed a lot. I want to measure the project from effort done point of view.
I think work execution should be measured in its own appropriate resource , so mhrs,m2, m3, tonnages etc. For the total rollup up a projects progress mhrs are fine as long as there are no purchases/deliveries involved.
A project with engineering/procurement and construction should be measured in cost or a cost-based weightfactor as this is the only common factor for all.
Last , i always prefer to make a combination of all three , quantities, mhrs and cost. More work at the start, but better control ovr the project.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Visit hpcconsult.co.uk it may help your problem.
See the 'Planning Academy' page.
Regards
Mike Harvey
There are many things that help to track the progress of the project. Materials are one. You must track your shop drawings (being submited by sub-contractors and approved by the architect) to insure that materials are recieved in a timely fashion so as not to delay progress. You should define items with long leed times. One item might delay several sub-contractors or delay the entire project. Even though you show progress as work complete to date compared against a baseline you need to track your materials. This is an important factor in schedualing a project.
William E. Stakelin
well, i think it went back to the same statement (..work execution should be measured in its own appropriate resource...). i think, it represents, a fact, that, every activity has its own way of evaluation and measurement.
my regargs for all,
mohd
I think the best solution to this discussion is EVPM.
Each activity's progress is measured in it's own units, translated to percent complete and used to compute earned value.
In this environment, the A/C unit discussion looses relevance, since all you do is compare a budget against a real progress.
The point is how much does each activity contribute to the whole effort. Well, you can manage that computing earned value in either dollars, man-hours, steel tons, concrete M3, etc.
Another point of view from the comments above:
Progress acomplished, by itself, does not really mean anything useful. What is more important is how much we have acomplished compared to our baseline progress metrics. In other words, have we acomplished as much as we need to, to date? You can measure this in terms of cost, duration or any resource metrics. It does not really matter as long as you are consistent with your measurements. Better yet, you should have two progress baseline curves. One for the earliest baseline schedule and another for the latest baseline schedule. Your actual progress should fall in between these two curves.
One word of caution: progress is only one side of the coin for making sure our project is on track.
I definitely agree, in our practice, we measure progress based on physical accomplishment. It not good to report that a particular equipment is there, of it is not installed it is still not a deliverable. It does not serve its function.
no body can disagree with that statement "work execution should be measured in its own appropriate resource" as progress measurements varies with every recourse involved and its activity. as far as electromechanical contractor, installing A/C chiller, is an important milestone. and for a civil one, block works is a time consuming activity. for a main contractor, who needs to know when will pay that much.
I do not agree with your with regard to cost, take and example of the A/C Chiller it costs a lot compared to 1 m sq of render lets say. When I deliver this chiller to site that does not mean that I have progressed a lot. I want to measure the project from effort done point of view.
I think work execution should be measured in its own appropriate resource , so mhrs,m2, m3, tonnages etc. For the total rollup up a projects progress mhrs are fine as long as there are no purchases/deliveries involved.
A project with engineering/procurement and construction should be measured in cost or a cost-based weightfactor as this is the only common factor for all.
Last , i always prefer to make a combination of all three , quantities, mhrs and cost. More work at the start, but better control ovr the project.