Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Level 3, 4 & 5 planning.

6 replies [Last post]
Neil Branigan
User offline. Last seen 8 years 43 weeks ago. Offline
Joined: 19 Dec 2006
Posts: 9
Groups: None
To all planners,

Being a rookie in the business, could anyone please educate me on the distinct differences between level 3, 4 & 5 planning. My belief is that level 3 is planning at a WBS level. Planning with activities below this - 5-10 approx. will be level 4 and level 5 is very detailed planning.
Could anyone please point me in the right direction on this one, please?

Cheers
Neil

Replies

D Artagnan
User offline. Last seen 2 years 49 weeks ago. Offline
Joined: 19 Sep 2008
Posts: 207

PEO has already shut down....i wish i had those papers

Clive Randall
User offline. Last seen 17 years 8 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
have a look at this
http://www.planningengineers.org/publications/papers.aspx

Personally

I always hammock down or up to get my levels
that way you dont have different programmes its all on the same page dead easy for progress monitoring and as builts.

Eugene K
User offline. Last seen 13 years 32 weeks ago. Offline
Joined: 18 Oct 2006
Posts: 47
Groups: GPC Malaysia
yes. i also find this classification of L1, L2.. L5 schedule very vague. the most "defined" classifaction i hv come across was this;

L1: (Owner’s) Development Programme (probably each project/subproj represented by 1 bar)
L2: L1 + Design/Procurement + Construction detail to major discipline
L3: (Contractor’s) Construction Programme = L2 + Construction detail to floor/area/zone, and trade/system
L4: (Contractor’s) Monthly Programme = Extract of L3 for 3 months (1 + 2 months Lookahead), detail to weekly work plan for current month.
L5: (Contractor’s) Weekly Programme = Extract of L4 for the month, detail to daily site work plan for current week.

I find this classification suitably definitive, the only thing i m not sure is... as a contractor preparing L3...
must we incorporate the the monthly details of L4 and weekly details of L5 into the L3?

Any ideas guys?
Rommel Ramirez
User offline. Last seen 15 years 42 weeks ago. Offline
Joined: 16 Mar 2007
Posts: 5
Groups: None
Guys,

L1 = Overall Project Master Programme
L2 = Summary Programme
a. design
b. production or construction
c. procurement
L3 = Detail Progamme
a. design
b. production or construction
c. procurement
L4 = Specific/Constraints Term
L5 = Subcontractors own Detailed Programme

Mabuhay!!!
Rommel
James Griffiths
User offline. Last seen 16 years 5 weeks ago. Offline
Joined: 19 May 2006
Posts: 435
Groups: None
Hi Neil,

Each WBS "level" is an increase in the amount of detail which an activity is sub-divided or grouped (if that makes any sense). A "level" is based on a WBS chart, where any group summary name that resides on the same row is also on the same "level". Each subsequent row of names equates to a new "level". Example:

L1 = CAR
L2 = Mechanical Electrical
L3 = ENGINE,BODY ECU, INSTRUMENTS
L4 = Further subdivisions of each component.


The number of "levels" that you have is wholly dependent upon how how many groupings and sub-groupings you wish to include by the time you reach the individual deliverable. However, you can execute a project and plan a project at any desired level. But the higher the level (3,4,5 ish), the less detail and definition is contained within the activity description. As a rough guide, you are correct in that, down to level 4/5, the activities may be poorly defined. Level 10 is probably excessively detailed.

HTH

James.
Nigel Winkley
User offline. Last seen 43 weeks 2 days ago. Offline
Joined: 11 May 2006
Posts: 187
Groups: The GrapeVine
Neil

If you have a look here, for an article by Gary France entitled "Standards for the Levels of a Programme or Schedule" it may help you.

http://www.planningengineers.org/publications/papers.aspx

Cheers

Nige