Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Combining all schedules or manage them with links!

6 replies [Last post]
tom huang
User offline. Last seen 12 years 23 weeks ago. Offline
Joined: 13 Aug 2006
Posts: 6
Groups: None
Running multi-contractors’ scheudles:

1. To combine thema all into one "giant" master schedule?!

2. Manage them separately (using P3e) with relative interfaces?!

There are pros and cons, personally I prefer the 2nd way. It’s quicker to run (if i only open project i need to work on) and more flexibility. Not to mention, only a handful of tasks are in progress any given time. I don’t really see the need to include everything in the same schedule!

What do you all think?!

Replies

Of course it is easier and more practical to work with the separate schedules.
But sometimes you will need to level resources that are used in different projects and manage total cost and material requirements and supplies.
Thus you need to be able to consolidate all projects in one master schedule to make necessary computations (resource, cost and material leveling) then to divide them back to manage separately.
John Lawson
User offline. Last seen 11 years 23 weeks ago. Offline
Joined: 6 Oct 2004
Posts: 113
Hi

Option 1. To combine them all into one "giant" master schedule?!

Reply: I would avoid this option at all costs, best to keep your projects in nice "easy lumps"

Option 2. Manage them separately (using P3e) with relative interfaces?!

Reply: This is way to go - this what the software was designed to do and it actuall does work, one job I was on we had over 600 projects all running together under P3e. This worked fine, mind would have hated to have had that lot in one one network!!

Regards

John
Nigel Winkley
User offline. Last seen 26 weeks 5 days ago. Offline
Joined: 11 May 2006
Posts: 187
Groups: The GrapeVine
Tom

Similar situation. I have to integrate three major projects - from P3, P3e and MSP. I have created milestones as a separate section and link via the milestones.

Minimal change to the "original" programme but links can easily be shown - both as "contract" or Schedule 11 and "planned" or the real timescales.

Stick with P3e - it’s what it’s for! So I am told...

Cheers

Nige
Marcio Sampaio
User offline. Last seen 12 years 7 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
I am now working with 5 big projects and i am managing all separate using P3e. It allow me to analyze all projects interfaces when necessary openning all at same time.

Regards.
Charleston-Joseph...
User offline. Last seen 3 years 12 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
hi,

Better manage the project using P3e/c or P5.

This is what P5 for, 32 bit unlimited unlimited ... capacity, functionality, etc.

Cheers,

Charlie
Abhijit Kulkarni
User offline. Last seen 2 years 41 weeks ago. Offline
Joined: 11 Nov 2003
Posts: 17
Have you tried sub projects Check in & Check out option?

You can create sub projects for your all schedules and bind them in one Main project and use Check in & Check out option to update separately and again merge with main project after updating.