1 pile(800 dia, 40m )/24 hr in very poor soil ,mud protected ( fill mud in the hole to protect it from collapse)

Member for

20 years 4 months

Thanks Bill for the insight information. I also spent a few years in the Guinean Golf and what’s for sure is that down times of 30 % are not unusual there!



I am awaiting soil investigations to refine estimate outputs.