Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Contiguous piling outputs

3 replies [Last post]
Hervé de Trogoff
User offline. Last seen 16 years 1 day ago. Offline
Joined: 22 Jun 2005
Posts: 4
Groups: None
Good morning all,

I am after some very specific piling output rates (in hrs per pile per rig), and was wondering whether anyone has data on the following:

- Type of pile: contiguous bored piling
- Dimensions: 1000mm Dia x 15.0m Length
- Methodology: rotary bored pile in cohesive soil (no stell casing)

I couldn’t quite find this info on the production rates available on the web site.

Any clue or historical data close to the above specs would help! Many thanks.

Hervé

Replies

Zhang Haixiang
User offline. Last seen 4 years 20 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
1 pile(800 dia, 40m )/24 hr in very poor soil ,mud protected ( fill mud in the hole to protect it from collapse)
Hervé de Trogoff
User offline. Last seen 16 years 1 day ago. Offline
Joined: 22 Jun 2005
Posts: 4
Groups: None
Thanks Bill for the insight information. I also spent a few years in the Guinean Golf and what’s for sure is that down times of 30 % are not unusual there!

I am awaiting soil investigations to refine estimate outputs.

Hervé
Bill Guthrie
User offline. Last seen 8 years 42 weeks ago. Offline
Joined: 14 Mar 2005
Posts: 262
Dear Herve

Many varables here.
type of soil,etc.etc.
availability of equipment. spares, back up rig.

Drilled 470 15lmpiles in Nigeria a few years back, and avg
3 15lm piles a day. however over a week, productivity dropped due to the 30% down time for equipment.Concrete piles are based on estruding pumped concrete and a specific pressure must be maintained when injection of concrete otherwise one must abandon hole and redo due to voids left in the pile.
therefore, need a spare drilling rig on standby and spare concrete pump on standby to maintain 3pd per week.

This will not help you much but it was a fact I had to live with on the project.