Progressing S Curve

Member for

20 years 7 months

Hi Daya,



I f your posting a mail to Sharol pls C.C. to me.



Thanx



Sunil

Member for

20 years 8 months

Dayanidhi,



You meant P3 or P3e? Do you have a step by step how to do it? Maybe a screen capture on how to do it?



Thanks.

Member for

22 years 7 months

Shahrol,



If you are using P3 schedule, then answer would be very simple. you should update your schedule periodically and use store period performance option to store the resources budgeted hours, when you want to revise the manhours, make a copy of the program, and update relevant budgeted hours of the activities in the program with revised manhours and export the resources budgeted manhours from this update and the baseline program in order to prepare a s-curve and see the difference where both curves cross each other will reflect from which date or week or month you need to have additional manhours. You may have to use timesheet to support the update of actual manhours at the site.



HTH



Daya

Member for

20 years 5 months

When revising the schedule at a certain data date in order to make it finish at the contract completion date, make sure to revise first relationship between sequential activities before doing any additions on the man-hours (resources). In producing the new S-curve, make sure:

1- to keep the history of the previous actual man-hours (or %)and cumulative man-hours (or %> I mean by %=planned man-hours on a certain period (week, month)/total man-hours (for the whole period of the contract)

2- to show on the graph, the previous S-curve and the new one and liaise at the data date of the revision the two S-curves in order to show the uplift (recovery)

3- to check the figures of the man-hours (or %) and compare it to the average periodical productive quantity that you can achieve.

4- The S-curve should be logic and smooth as much as you can. for ex. if your recovery requires additional resources, you cannot provide them quickly, this should be shown on the S-curve.

5- You need always to remember that you curve has an S shape not an I or other shapes :)



Regards,

J. Daniel

Member for

22 years 6 months

Let me share my experience on this issue.

Half way through a project, we were 7 % (roughly 2.5 months behind the schedule) & we had to revise the schedule & keep the end date same.

Choose the date from which you are revising. Make all actuals accordingly. Split the in progress activities ompleted & not-started portions. Re-schedule the balance activities accordingly.

The new (excluding actuals) shall give you the remaining S-curve.



Hope this works!

Regards



Dattatreya

Member for

20 years 8 months

Revise the schedule. Pull back all the activities to the contract finishing date. Obviously, you need to increase the resources to complete the project on time since you already encounter a delay upto 10~15 days.



Derive the new manhours from tabular report and update the s-curve.



Regards.