can you please advise if there is any software that makes the mapping excersise and provide the level 3 activity level of the primavera schedule budgeted cost.
I am trying to solve the issue utilizing Ms Excel however there are a lot of parameters needs to be manually inserted and calcualted in order to reach to a presentable maapping sheet and an acceptable weight factors.
can you please advise if there is any software that makes the mapping excersise and provide the level 3 activity level of the primavera schedule budgeted cost.
I am trying to solve the issue utilizing Ms Excel however there are a lot of parameters needs to be manually inserted and calcualted in order to reach to a presentable maapping sheet and an acceptable weight factors.
thank you in advance
Member for
22 years 7 months
Member for22 years7 months
Submitted by Dayanidhi Dhandapany on Sat, 2004-07-24 06:17
its a Valuable Information, but i need more specific information about "WC", and some theoritical information about the integration to write it in my Master Research.
Sincerely Your
Dipl.Eng- ALassam Ghanem
Member for
23 years 3 months
Member for23 years3 months
Submitted by Rahmat Hidayat on Wed, 2004-05-26 22:57
Based on my experience in some EPC Projects, WBS is unique for different projects and developed specifically in accordance with the project Scope of Work (SOW). Different project will have different process, facilities, unit, etc. Anyway, in a certain level of WBS there should be a level for "standard work category (WC)". This WC is same for any kind of projects (example: cocrete work, tank erection, cable pulling, etc).
CBS is usually a Contractor standard cost code and it should have also a certain level for WC. Linking b/w WBS and CBS is here, WC of WBS and CBS. On the other term, we name this WC level as Work Packages. Lower levels are cost-based activities and their steps.
When established, we can apply Earned Value Method to measure performance in every level of WBS or CBS.
Primavera implements this kind of integration system.
Member for
14 years 3 monthshello all, can you please
hello all,
can you please advise if there is any software that makes the mapping excersise and provide the level 3 activity level of the primavera schedule budgeted cost.
I am trying to solve the issue utilizing Ms Excel however there are a lot of parameters needs to be manually inserted and calcualted in order to reach to a presentable maapping sheet and an acceptable weight factors.
thank you in advance
Member for
14 years 3 monthshello all, can you please
hello all,
can you please advise if there is any software that makes the mapping excersise and provide the level 3 activity level of the primavera schedule budgeted cost.
I am trying to solve the issue utilizing Ms Excel however there are a lot of parameters needs to be manually inserted and calcualted in order to reach to a presentable maapping sheet and an acceptable weight factors.
thank you in advance
Member for
22 years 7 monthsRE: CBS, WBS Integration
Similar Discussion: CBS, WBS Integration
Member for
16 years 9 monthsRE: CBS, WBS Integration
Dear Sir Rahmat Hidayat
its a Valuable Information, but i need more specific information about "WC", and some theoritical information about the integration to write it in my Master Research.
Sincerely Your
Dipl.Eng- ALassam Ghanem
Member for
23 years 3 monthsRE: CBS, WBS Integration
Based on my experience in some EPC Projects, WBS is unique for different projects and developed specifically in accordance with the project Scope of Work (SOW). Different project will have different process, facilities, unit, etc. Anyway, in a certain level of WBS there should be a level for "standard work category (WC)". This WC is same for any kind of projects (example: cocrete work, tank erection, cable pulling, etc).
CBS is usually a Contractor standard cost code and it should have also a certain level for WC. Linking b/w WBS and CBS is here, WC of WBS and CBS. On the other term, we name this WC level as Work Packages. Lower levels are cost-based activities and their steps.
When established, we can apply Earned Value Method to measure performance in every level of WBS or CBS.
Primavera implements this kind of integration system.