Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

CBS, WBS Integration

5 replies [Last post]
ALassam Ghanem
User offline. Last seen 17 years 45 weeks ago. Offline
Joined: 19 May 2004
Posts: 21
Groups: None
Cost Breakdown Structure, Work Breakdown Structure are an essential parts in Costuction Projects Management. an integration between WBS and CBS are an important matter to Manage and Control The construction project.
Please, I need Some Information about CBS, WBS and the Advanteges of Integration between them in construction projects."Free Books, Articals, Information"

Heartly Greetings

Replies

Sami Abualheijaa
User offline. Last seen 3 years 46 weeks ago. Offline
Joined: 24 Jul 2011
Posts: 10
Groups: None

hello all, 

can you please advise if there is any software that makes the mapping excersise and provide the level 3 activity level of the primavera schedule budgeted cost. 

I am trying to solve the issue utilizing Ms Excel however there are a lot of parameters needs to be manually inserted and calcualted in order to reach to a presentable maapping sheet and an acceptable weight factors.

 

thank you in advance

Sami Abualheijaa
User offline. Last seen 3 years 46 weeks ago. Offline
Joined: 24 Jul 2011
Posts: 10
Groups: None

hello all, 

can you please advise if there is any software that makes the mapping excersise and provide the level 3 activity level of the primavera schedule budgeted cost. 

I am trying to solve the issue utilizing Ms Excel however there are a lot of parameters needs to be manually inserted and calcualted in order to reach to a presentable maapping sheet and an acceptable weight factors.

 

thank you in advance

Dayanidhi Dhandapany
User offline. Last seen 3 years 34 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
Similar Discussion: CBS, WBS Integration
Forum Guest
User offline. Last seen 18 weeks 2 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Dear Sir Rahmat Hidayat
its a Valuable Information, but i need more specific information about "WC", and some theoritical information about the integration to write it in my Master Research.
Sincerely Your
Dipl.Eng- ALassam Ghanem
Rahmat Hidayat
User offline. Last seen 3 weeks 20 hours ago. Offline
Joined: 30 Jul 2002
Posts: 82
Based on my experience in some EPC Projects, WBS is unique for different projects and developed specifically in accordance with the project Scope of Work (SOW). Different project will have different process, facilities, unit, etc. Anyway, in a certain level of WBS there should be a level for "standard work category (WC)". This WC is same for any kind of projects (example: cocrete work, tank erection, cable pulling, etc).

CBS is usually a Contractor standard cost code and it should have also a certain level for WC. Linking b/w WBS and CBS is here, WC of WBS and CBS. On the other term, we name this WC level as Work Packages. Lower levels are cost-based activities and their steps.

When established, we can apply Earned Value Method to measure performance in every level of WBS or CBS.

Primavera implements this kind of integration system.