HI! GUYS
I want your help as to how i should proceed with the development of Schedule for Engineering Activities , loaded with resource as Mahours.
I have with me the entire break up of Documents and the Manhours as the INput to the schedule.
My techniques , initially was to Import all this to P3 and run a Global change , with QTY(No. pf Docs) X Rate( Manhours/Doc) = total Manhours.
BUt there wasa hotch that the activities would be totalling upto 1000 nos. with each document to be racked , physically with only 7 months schedule.
What should i do in this case.
please Advise.
I am also tracking the progress of the documents using ACCESS database.
The weightings of the docs also are imbibed through the ACCESS d/b.
I waould just plug in the progress percentage into P3 from access D/b per dividual Doc(or type of doc) and get to match the Progress percentage that ACcess gives me .
Is this a reasonable exercise to do knowing well taht i have only 7 months Project Period and fortnightly updation.
Please Advise , the course of action that need to be followed , in this case, cos i am setting up a Project Control process also.
Thx.