The performance % complete is not equal cost % complete

1 reply [Last post]
yahya atef
User offline. Last seen 42 weeks 2 days ago. Offline
Joined: 3 May 2017
Posts: 4
Groups: None

I make revised plan for my project but there is a problem the performance % complete does not equal the cost % complete ?

 

Replies

Rodel Marasigan
User offline. Last seen 1 day 14 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Performance % Complete:

The Performance % Complete is used to compute earned value and may be based on the Activity % Complete, the 0/100 rule, the 50/50 rule, or other techniques, depending on the method used to calculate the earned-value percent complete for the activity's Work Breakdown Structure (WBS). The Performance % Complete specifies the percentage of the activity's planned value that has been earned so far. On the other hand, the cost % complete is calculated based on the actual costs entered in the Actual Cost field, including labor, non-labor, materials, and expenses. To match it, you can adjust the cost value to align with the earned value.