Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

The performance % complete is not equal cost % complete

1 reply [Last post]
yahya atef
User offline. Last seen 47 weeks 2 days ago. Offline
Joined: 3 May 2017
Posts: 4
Groups: None

I make revised plan for my project but there is a problem the performance % complete does not equal the cost % complete ?

 

Replies

Rodel Marasigan
User offline. Last seen 5 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Performance % Complete:

The Performance % Complete is used to compute earned value and may be based on the Activity % Complete, the 0/100 rule, the 50/50 rule, or other techniques, depending on the method used to calculate the earned-value percent complete for the activity's Work Breakdown Structure (WBS). The Performance % Complete specifies the percentage of the activity's planned value that has been earned so far. On the other hand, the cost % complete is calculated based on the actual costs entered in the Actual Cost field, including labor, non-labor, materials, and expenses. To match it, you can adjust the cost value to align with the earned value.