Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Why 6?

4 replies [Last post]
Hemant Shewnarain
User offline. Last seen 18 years 33 weeks ago. Offline
Joined: 12 Apr 2006
Posts: 3
Groups: None
Hi,

just started to learn about Project Managment and reading about PERT/CPM.

why do u divide by 6? and why do u multiply by 4?

Expected Time:
t = (a + 4m + b)/6

Replies

pmkb .
User offline. Last seen 13 years 25 weeks ago. Offline
Joined: 15 Sep 2005
Posts: 79
Groups: None
It’s a weighted average. The 4 and 6 are related to each other in that you have 4 parts of one element and 1 part each of two other elements for 6 total parts. The equation could just as easily have 6/8 instead of 4/6 if the probable estimate was deemed to have a higher weight.

I do not know why 4/6 is generally used as opposed to 6/8, 10/12 or any other weighting factor.

Stacy
Project Management Knowledge Base
Clive Randall
User offline. Last seen 16 years 49 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
Charlie
Welcomne back
Bell shaped graph
Standard deviation
Not sure higher maths is required
Standard deviation is very simple ask any site engineer who has worked out the results for concrete cube testing.
But why 6 I thought 32 was the answer
Clive
Charleston-Joseph...
User offline. Last seen 3 years 17 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Hello,

This is related to the theory of probability.

The graph generated is a bell shape.

The equation is similar to mean average.

I hope you understand and recall your mathematics or higher algebra, differential calculus, intergral calculus, engineering mathtmatics or any subject related to mathematics.

Cheers,

Charlie
Steven Oliver
User offline. Last seen 12 years 1 week ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Where

a = pessimistic duration

4m = 4 * probable duration

b = optimistic duration

generally accepted "rule of thumb". You could equally propose your own method.

(((a+b)/2)+m)/2) for instance