Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Multiple import of risks to Primavera P6

No replies
Dejan Kezic
User offline. Last seen 1 year 37 weeks ago. Offline
Joined: 21 Mar 2018
Posts: 6
Groups: None

Hi everyone,

Is there solution ti import (through Excel) risks to large number of activities in P6 schedule?

Similar to importing of activities and/or resources, I would like to define several different risks and then instead of using manual method in P6 to export file to Excel, then prepare it for importing by coping risks to different activities and return it through import.

I have tried it, but I can not find Risks in Available Options in Export dialogues.

 

Thank you in advance!

Santosh Bhat
User offline. Last seen 27 weeks 2 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

Dejan,

Interesting, Doesn't look like Oracle have made Risks available to be viewed in the export templates, or in columns or Grouping/Sort, even though they are linked to activities.

So there is no way to either populate the Risks or to assign them to activities.

Out of interest - what are you intending to use this functionality for, other than registering risks against activities, the Risk module of P6, doesn't do much.