Hi Steve,
I cannot see your screenshot. If you set it correctly under the Project WBS module then the best way to check it is to show the Cost Performance Index (CPI) on the column so you know if the CPI for that activity is equal to 0.94. It maybe equal to 1.
Cost Performance Index (CPI) is calculated EV/AC. If a value is less than 1 then your AC have exeeded the PV.