Hi All,
I am new to scheduling and I have a question.
Before asking my question, just wanted to give you a notice what we generally do( maybe this is a common proceduer in every office):
There is a baseline of the project which is assigned in " Project Baseline" and there is another one which is for the last month and it is assigned in " primary baseline".
I have updated the schedule in late October and have put all the actuals and everything related to the programme in the software. After that I have baslined the programme and named in for " October" and assigned this baseline for " Primary Baseline".
Now I want to create a layout for myself to see the differences between " September" and " October"
1- Are the assigned baseline Okay? " Project baseline: The main baseline of the project, " Primary Baseline : October's baseline with a data date of 1st of November"
2- What columns should I put there to see the changes?
I know you may say that all of them can be there, but I want the ones which are useful for tracking the changes between these two months.( September and October).
Activity NameStart Finish BL1 Start BL1 Finish BL1 Actual Start BL1 Actual Finish BL1 Activity Status Actual Duration BL Project Actual Duration BL1 Actual Duration Original Duration BL Project Duration BL1 Duration At Completion Duration Remaining Duration BL Project Remaining Duration BL1 Remaining Duration BL Project Total Float Total Float BL1 Total Float Variance - BL1 Duration Variance - BL Project Duration Variance - BL1 Start Date Variance - BL1 Finish Date BL1 Physical % Complete BL Project Completed Activities BL1 Completed Activities BL Project In-Progress Activities BL1 In-Progress Activities BL Project Not-Started Activities Actual Completed Activities Actual In-Progress Activities Actual Not-Started Activities BL1 Not-Started Activities
Abbas, yes. September
Project baseline - data date the Project Start date
Primary Baseline - data date one month ago
Current Project - Data date 'now'