Resource Assignment Layout

2 replies [Last post]
Shahrol Sabaruddin
User offline. Last seen 13 years 38 weeks ago. Offline
Joined: 8 Feb 2005
Posts: 21
How to get only oustanding or in progress (Physical % Complete between 0% to 99%) Resource Assignment layout in P3e. I’m using P3e 3.5.1 by the way.

I’ve tried but it’ll will shows Resource Assignment with all activities including 100% complete. Could somebody help me.

Replies

Shahrol Sabaruddin
User offline. Last seen 13 years 38 weeks ago. Offline
Joined: 8 Feb 2005
Posts: 21
Thanks, Niek. It help!
Niek Zonneveld
User offline. Last seen 3 weeks 5 days ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None
Shahrol,

100% complete activities have an actual finish, so if you filter on: "actual finish equals [empty]" you’ll get what you are looking for.

Cheers,

Niek.