Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Issues when inserting P6 Programme

No replies
Eliuh Akinpeloye
User offline. Last seen 2 years 11 weeks ago. Offline
Joined: 14 Aug 2018
Posts: 3
Groups: None

Hello house,

I will appreciate any help on the issue I am currently facing:

I copied a subcontractor Xer File to my Master Schedule . This plan was moved to a WBS within the master schedule, however I am now facing an issue where  a number of activities adopted a global calendar therefore their dates are all over the place

 

Is there a way I could this or I'll need to go back to the inserted programme and change the calendar manually ?

Secondly, when I aligned the calendar and schedule the programme, I notice the inserted programme now in a WBS of the master schedule is generating a negative float despite maintaning the same DD to the last secs.

Any guidance on the above 2 issues will be highly appreciated

 

Zoltan Palffy
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

3 options

option #1

you can choose to not import calendars during the import process

Option #2

add column for calendars and do the 1st activity and the do a fill down

Option #3

run a global change to make all of the calendars the same 

Zoltan Palffy
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

3 options

option #1

you can choose to not import calendars during the import process

Option #2

add column for calendars and do the 1st activity and the do a fill down

Option #3

run a global change to make all of the calendars the same