Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Primavera Visualizer Scheduler Compare - can you export it to excel?

1 reply [Last post]
John Reeves
User offline. Last seen 23 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Primavera Visualizer Scheduler Compare - can you export it to excel?  It has gotten better, it is still weird and clunky though - I can only seem to print of the screen.  Can you export to excel, I tried to copy and paste to excel - that did not work too well.

Replies

Rodel Marasigan
User offline. Last seen 13 weeks 6 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Yes you can. Go to Option and select General Tab. Select CSV and select the file destination and file name. Click Save and Draw. Then go to the folder where you save. Double click the csv file and it will open in Excel. See below: P6-Schedule-Comparison