Space in Bar

5 replies [Last post]
moutaz aldeib
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Greetings Planners

I am updating a baseline schedule, some of the activities that have actual start but not yet completed, their bar after the data date bar is not continous, there is a space between the data date and then the bar for the next period starts.

Is there any explanation for this.

Regards,

Muataz

Replies

Zoltan Palffy
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

it may well be ahead of the planned or baseline schedule 

Santosh Bhat
User offline. Last seen 5 weeks 6 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

You have retained logic running through the predecessors of that task, check the relationships have been upheld as you've enterered the actual dates.

Jerome Odeh
User offline. Last seen 16 hours 22 min ago. Offline
Joined: 19 Jan 2004
Posts: 107

Hi Zoltan,

Won't changing Actual Work setting to Current Bar make it show progress beyond data date?

Jerome

Zoltan Palffy
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

here is the fix go to bars 

go to the actual work bar and in the 3rd column (time scale) chneg this setting from Actual bar to Current bar

Jerome Odeh
User offline. Last seen 16 hours 22 min ago. Offline
Joined: 19 Jan 2004
Posts: 107

Moutaz,

Most likely the your calendar start time is 08:00 while your data date time is 00:00

Check this blog post for details

https://www.plannersplace.com/blog/how-remove-gaps-after-data-date-primavera-p6

 

=jerome