breaking schudule bar into 2 bar

2 replies [Last post]
Ruel Camaquin
User offline. Last seen 4 years 5 days ago. Offline
Joined: 16 Nov 2008
Posts: 100
Just like to know if it is possible in P6 to break a single schedule bar into 2 activities?

For example, i would like to show the procurement start date then followed by the activity start-end dates.

Thanks & Cheers!

Replies

Ruel Camaquin
User offline. Last seen 4 years 5 days ago. Offline
Joined: 16 Nov 2008
Posts: 100
Oliver,

Thanks for that.

Cheers!
Oliver Melling
User offline. Last seen 4 years 51 weeks ago. Offline
Joined: 24 Apr 2007
Posts: 595
Groups: The GrapeVine
Ruel,

You cannot split tasks in P6 when planning, as far as i know.

You will need to put in multiple tasks.

The only scenario where you can split a task is during updating progress, when the suspend and resume function can be used.