F&D of an elevator? Average Fabrication & Delivery Time for a "New" elevator?

No replies
John Reeves
User offline. Last seen 17 weeks 2 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

F&D of an elevator?  Average Fabrication & Delivery Time for a "New" elevator?  I googled it - it said 6 months from time you hire consultant to deliverly.  Lets say for public project - I have seen 6 months just for F&D - what would be a reasonable duration to use?

PS, I think escalators are even longer - I think there are only 2 manufacturers in the Western World.