Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Variance Showing in p6 even though Activity no Budget

1 reply [Last post]
Patrick Walsh
User offline. Last seen 5 weeks 2 days ago. Offline
Joined: 11 Sep 2013
Posts: 5
Groups: None

hello

I have an activity showing a cost variance in the variance column even though that activity does not have a budgeted total cost.

Please help, it has to be a setting issue i think....

Replies

Zoltan Palffy
User offline. Last seen 12 weeks 10 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

if it has a variance it must be comparing against something do you have a baseline attached ?

see if there is an actual cost  or a cost to complete ?

if there are values here it will still show a variance

look at previous period costs