Variance Showing in p6 even though Activity no Budget

hello

I have an activity showing a cost variance in the variance column even though that activity does not have a budgeted total cost.

Please help, it has to be a setting issue i think....

Z
Zoltan Palffy 👤 Member for 17 years

if it has a variance it must be comparing against something do you have a baseline attached ?

see if there is an actual cost  or a cost to complete ?

if there are values here it will still show a variance

look at previous period costs 