Variance Showing in p6 even though Activity no Budget

hello

I have an activity showing a cost variance in the variance column even though that activity does not have a budgeted total cost.

Please help, it has to be a setting issue i think....

Z
Zoltan Palffy 👤 Member for 16 years 11 months

if it has a variance it must be comparing against something do you have a baseline attached ?

see if there is an actual cost  or a cost to complete ?

if there are values here it will still show a variance

look at previous period costs 

Forum Sponsor

Top Posters

bal aji
2 posts
Lee Mallek
23 posts
Syed Shoeb
0 posts
Viet Tran
8 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts