Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Imported Project Without Baseline

2 replies [Last post]
irfan morkoc
User offline. Last seen 4 years 9 weeks ago. Offline
Joined: 8 Mar 2013
Posts: 10
Groups: None

Hi,

I have imported a file without its baseline. But I see baseline start/finishes dates are different than project start/finish dates. I checked there is no assigned baseline. I expect if there is no baseline assigned to the project then baseline dates should be equal to project dates.

Could you please explain ?

Regards

Replies

irfan morkoc
User offline. Last seen 4 years 9 weeks ago. Offline
Joined: 8 Mar 2013
Posts: 10
Groups: None

Thank you very much Alexandre.