Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6 Filter

2 replies [Last post]
Heather Hadley
User offline. Last seen 2 years 40 weeks ago. Offline
Joined: 29 Jan 2019
Posts: 27
Groups: None

I'm hoping someone can help me.  I need to filter my P6 schedule for a 2 week look ahead HOWEVER the PM is looking to also see all milestones - not just the ones within that 2 week period.

 

Can anyone help?

Replies

Heather Hadley
User offline. Last seen 2 years 40 weeks ago. Offline
Joined: 29 Jan 2019
Posts: 27
Groups: None

Thanks!!

Santosh Bhat
User offline. Last seen 4 weeks 6 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

Heather,

Use the top row of a filter to change the statement from "all" to "any" and then you can have three rows like this

Row 1) Finish is less than DD+2w (if you want two weeks from the data date, CD+2w if you want from the current date)

OR

Row 2) Activity Type = Start Milestone

OR

Row 3) Activity Type = Finish Milestone