Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Problems in importing Excel files

3 replies [Last post]
mohamed gomaa
User offline. Last seen 5 years 11 weeks ago. Offline
Joined: 4 Dec 2009
Posts: 4

Hi Everybody ,

I exported a resource assignement excel file to change budgeted units and other data, when importing the resource is doubled (as shown in the attched image) , i recalculated the assignement costs , but still i will have to manualy remove the doubled resource and this will be a tediuos process as there is a lot of af activities .

Hope to find a fix to this problem.

Regardswysiwyg_imageupload::

Replies

Zoltan Palffy
User offline. Last seen 1 week 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

of course it worked

mohamed gomaa
User offline. Last seen 5 years 11 weeks ago. Offline
Joined: 4 Dec 2009
Posts: 4

Thanks Zoltan , it worked.

Regards

Zoltan Palffy
User offline. Last seen 1 week 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

go to Projects DIRECTORY and make sure that your project is open

then click on teh Resources tab at the bottom then look on the lower left where it says Resource Assignment

UNCHECK Resources can be assigned to the same activity more than once.