List of activities in excel - Best way to copy to Primavera

3 replies [Last post]
Yaron Avramov
User offline. Last seen 5 years 15 weeks ago. Offline
Joined: 28 Apr 2013
Posts: 3
Groups: None

I have a list of about 1000 activities in an Excel file, and I want to copy them to a project in Primavera.

What would be the easiest way to do that?

I only need to copy the activity names, I will set the relationships, durations and dates later.

Any suggestions? 

Thanks for any help.

Replies

Johannes Vandenberg
User offline. Last seen 1 year 12 weeks ago. Offline
Joined: 21 Jan 2010
Posts: 234

Hi Yaron

Perfectely  explained by Zoltan & Santosh.  If you like to see more check out this screen caputure.

Zoltan Palffy
User offline. Last seen 27 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you will have to assign the proper wbs after importing the activities 

Santosh Bhat
User offline. Last seen 51 weeks 1 day ago. Offline
Joined: 15 Apr 2005
Posts: 381

Excel import.

Within P6, create a single activity, then FILE>EXPORT>XLS>ACTIVITIES> and set a locaton and file name to export to.

Open this file in Excel, then use the single activity as a template and populate the remaining rows. Save and close the xls file.

Back in P6 FILE>IMPORT>XLS and point to the saved xls file and you should have a list of activities to work with.