Hi All,
I have created an integrated schedule with LOEs from Start and Finish Milestones in individual projects (a total of 35) by externally linking the LOE in the integrated schedule with the milestones in the individual projects.
My problem is that I want to show on the Gantt Chart the LOE created for that scope in an individual project as well as a basline bar from that individual project. For example, Start / Finish Milestones were Jan 1 and Jun 1 in the baseline. Now they are Jan 15 and Jun 2 in the current schedule which is what my LOE will show. How do I show the Jan 1 and Jun 1 as a bar in my gantt chart with the LOE bar?
And, just to make it even more complicated, is there a way to show an earlier baseline in there as well - say the project has originally baselined the dates as Oct 31 and Mar 7. Is it possible to show the current LOE bar, the Jan 1 to Jun 1 baseline bar and the Oct 31 to Mar 7 bar all on the same gantt chart. I've been trying to mess around with the Assign/Maintain baselines but am getting frustrated....
Any help is greatly appreciated!!
Thanks
Heather
Replies