Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Login problem P6 "You are not authorized to run the application. Please contact your administrator." on windows 10 pro

8 replies [Last post]
Sprogo Priaso
User offline. Last seen 4 years 34 weeks ago. Offline
Joined: 17 Dec 2019
Posts: 10
Groups: None

 

I can not login to succesfully installed P6 PPM on windows 10 Pro desktop computer.

 

If wrong credentials are entered on login page of P6, it says “Invalid user name or password. Please try again”. If correct credentials are entered, it says “You are not authorized to run the application. Please contact your administrator.”.

 

I installed the same files to windows 10 home computer, it is working without

 

Can anyone help me to understand and solve this problem.

Replies

ozgur karaguzel
User offline. Last seen 1 year 6 weeks ago. Offline
Joined: 16 Sep 2008
Posts: 11
Groups: None

I'm getting the same error. is there a solution? Win 11 pro

ozgur karaguzel
User offline. Last seen 1 year 6 weeks ago. Offline
Joined: 16 Sep 2008
Posts: 11
Groups: None

I'm getting the same error. is there a solution? Win 11 pro

ozgur karaguzel
User offline. Last seen 1 year 6 weeks ago. Offline
Joined: 16 Sep 2008
Posts: 11
Groups: None

I'm getting the same error. is there a solution? Win 11 pro

ozgur karaguzel
User offline. Last seen 1 year 6 weeks ago. Offline
Joined: 16 Sep 2008
Posts: 11
Groups: None

I'm getting the same error. is there a solution? Win 11 pro

ozgur karaguzel
User offline. Last seen 1 year 6 weeks ago. Offline
Joined: 16 Sep 2008
Posts: 11
Groups: None

I'm getting the same error. is there a solution?

Zoltan Palffy
User offline. Last seen 20 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you have to click up top on databases NOT login and type this 

try this click on the drop down where it says database

select configure

select next 

in the user name put in pubprm$pm

for the password put in admin

Santosh Bhat
User offline. Last seen 12 weeks 4 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

Sorry without knowing more about your setup its difficult to asses. But knowing its a sQLite DB try the following:

1) Start P6 accplication as an Administrator

2) Copy the SQLite file to another directory, say your desktop and try creating a new DB connection in P6 to this copied file. Your Win PRO may have restricted rights to access files etc and this might be causing the issue.

Sprogo Priaso
User offline. Last seen 4 years 34 weeks ago. Offline
Joined: 17 Dec 2019
Posts: 10
Groups: None

Unfortunatelly thats not the option. user name admin, password is also admin.

Database is Sqlite.

My analysis steps are:

1) The P6 software is working as login screen pops up without an error. 

2) Databese and again p6 is working too as login attempts are rejected if wrong credentials (either user name or password) were used.

3) Response of databse for login attempt with correct credentials, says; either;

a) This user (admin) has no right to connec to to this database

b) This user (admin) has no permission to run an application module or something.

4) This situation happens because of either operating system (windows 10 pro) of my desktop pc, or security setups or privacy setups, or something about UAC.  Because it works on windos 10 HOME sysem on my notebook.

 But my technical knowledge is not enough to find a solution or analize it more deeper.

Santosh Bhat
User offline. Last seen 12 weeks 4 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

Ok my guess is that you're trying to connect to a local SQLite Database called PMDB. When you were creating this database, you would've had to create a user, chances are the username was "admin" and you'll need to remember what you set as the password, it may even be blank if you didn't set one!

Sprogo Priaso
User offline. Last seen 4 years 34 weeks ago. Offline
Joined: 17 Dec 2019
Posts: 10
Groups: None

Zoltan,

 

Unfortunatelly it doesn't work.

 

7183
p6_login.jpg

Sprogo Priaso
User offline. Last seen 4 years 34 weeks ago. Offline
Joined: 17 Dec 2019
Posts: 10
Groups: None

Santosh,

I am using P6 Professional 18.8  PPM

Yes I can not find user administration menu or part.  I suppose you are right but it is weird since it works on windows 10 home notebook but not works on windows 10 pro although all installation steps are exactly the same. 

Zoltan Palffy
User offline. Last seen 20 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

try this click on the drop down where it says database

select configure

select next 

in the user name put in pubprm$pm

for the password put in what was defined during installation of P6

Santosh Bhat
User offline. Last seen 12 weeks 4 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

Which version of P6 are you using? more recent versions of P6 PPM installed as standalone SQLite database don't invlude any user administration. The error you're receviing looks like the user hsan't been given the right module rights in the P6 database.