Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Export Cost and Resources

3 replies [Last post]
Muhammad Saqib
User offline. Last seen 5 years 6 days ago. Offline
Joined: 25 Oct 2018
Posts: 35
Groups: None

Dear All,

I want to export my P6 file which is Resource and Cost loaded. I want to export the same file which includes both these data.

When i export the file by choosing project only option , the budgeted cost data is not displayed while importing this file .

 

Secondly, if i want to send the file which includes only activities and date, then how to hide the cost and resources.

 

Please explain both these methods. i would really appreciate

 

Thirdly, kindly explain the export options (project only and resource only)

 

Thanks

 

Regards,

Saqib

Replies

Muhammad Saqib
User offline. Last seen 5 years 6 days ago. Offline
Joined: 25 Oct 2018
Posts: 35
Groups: None

Thank You so much Alexandra.

God Bless You

Mohammad Zishan
User offline. Last seen 5 years 2 weeks ago. Offline
Joined: 2 Sep 2019
Posts: 3
Groups: None

Dear all

 

when i updating the project if i miss some thing then i want to go back few step . in Primavera P6 there are any sortcut option to go back 1,2,3 step.

 

please reply 

 

thanks